Novellum
Novellum
  • Home
  • Projects
    • Research & Development
    • Specialized Industrial
    • Mining
    • Automotive Infrastructure
    • Defense
  • Contact Us
  • More
    • Home
    • Projects
      • Research & Development
      • Specialized Industrial
      • Mining
      • Automotive Infrastructure
      • Defense
    • Contact Us
  • Home
  • Projects
    • Research & Development
    • Specialized Industrial
    • Mining
    • Automotive Infrastructure
    • Defense
  • Contact Us

Water Test Facility Waste Water Transfer


Project Details:

Total Value:            $165 000
Year Completed:    2023
Duration:                6 months


Background:       

There was a requirement to transfer the waste water from the water test facility to the effluent plant at the paintshop.


Description:        

A pipe route through the production facility was planned and the hydraulic design done.  A 50mm galvanized pipeline was installed over a distance of approximately 0.5 km. Two pumps with bag filters were installed operating on a standby and duty pump principle.

Back to Automotive

Copyright © 2026 Novellum - All Rights Reserved.

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept